Description of the investment:

The Jankowice Coal Mine is one of several companies belonging to Kompania Węglowa S.A. During the expansion of the mine and upon commencement of excavation of new coal beds, it turned out that it was necessary to build a mine water main pumping station 1050m below the ground level.

Scope of work:

• performance of mining work at the pumping station
• construction of the pumping station with installation of 3 pumps
• delivery and installation of a switchgear center powering the pumps
• delivery and installation of Control and Measurement Equipment and Automation
and control system along with a visualisation system
• preparation of as-built documentation
• acceptance tests and operator training

Project type Installation
Period 2011-2012
Total Value N/A
Client Kompania Węglowa SA